Mud_Logging_Report


[Columns] [Composed Of] [Referenced By] [Refers To]

General Information

[Next]
Name Mud_Logging_Report
Entity Type Table
Description A periodic report on mud gas properties.
Submodel WS_Activity
Entity Scope Project
Primary Key Id
Natural Key
Generalizations Borehole_Activity , Wellsite_Activity , Activity , Entity , IT_Object , Tracked_Object
Specializations


Columns

[Previous] [Next] [Top]
NameValue Domain /
Measurement
DescriptionRequired /
Default
Type
Activity_Program_Id Activity_Program
Reference to the program during which the activity was performed. No
NUMBER(38)
Activity_State STRING64
NA
The current state, or status, of the activity. Activity state is a refinement of the lifecycle indicator Existence_Kind. For example, a drilling job whose Existence_Kind is "Actual" could have an activity state of "turning to the right", "suspended due to weather", or "tool makeup or breakdown". An activity whose Existence_Kind is "Required" could have State values like "under investigation", "proposed" and "AFE approved". Note: The valid list of activity states will vary from one kind of activity to another, so the values entered into this column are not validated via a lookup table. No
VARCHAR2(64)
Activity_Template_Id Activity_Template
The Activity is an activation of, and is characterized by the associated Activity_Template. No
NUMBER(38)
Actual_Carbide_Lag_Time double
Time
The actual Carbide Lag Time recorded during this period No
NUMBER
Avg_Carbide_Test_Hole_Diam double
Cylinder_Diameter
The average hole diameter for the Carbide_Lag Test No
NUMBER
Avg_Connection_Gas double
No_Unit
The average connection gas value of the mud during the reporting period No
NUMBER
Avg_Hydrogen_Sulfide_Conc double
Concentration
The average hydrogen sulfide content of the mud during the reporting period No
NUMBER
Avg_Trip_Gas double
No_Unit
The average trip gas value of the mud during the reporting period No
NUMBER
Borehole_Id Borehole
To identify the borehole Yes
NUMBER(38)
DST_Run_Flag boolean
NA
A flag to denote whether a Drill String Test were run during the period of this report. No
NUMBER(1)
End_Date DATE
NA
The date and time at which the activity will end or did end. For planned activities, this would be expected end date. No
DATE
End_MD double
Depth
Measured depth at the end of the activity or proposed depth end of the activity. No
NUMBER
Existence_Kind REF_EXISTENCE_KIND
NA
A reference value that describes the state of existence in the lifecycle of the entity, for example, Planned, Predicted, Required, Simulated, and Actual. Yes
Actual
VARCHAR2(64)
External_Reference STRING64
NA
A value that is used by an external organization to reference this activity. For example, if an external organization is hired to perform this activity, this column could be used to store the work order or purchase order number that organization uses to reference this activity. No
VARCHAR2(64)
GUID STRING128
NA
Globally Unique IDentifier for an instance of a class. This GUID is not generated by the database, but is the GUID used by the application on first access of this object. Use of this property is optional and completely under the control of application developers. No
VARCHAR2(128)
Id ID
No_Unit
Unique identifier for this entity. Yes
NUMBER(38)
Insert_Date DATE
NA
Date the entity was created in the repository No
DATE
Insert_User STRING64
NA
The name of the user responsible for the creation of this entity in the repository. No
VARCHAR2(64)
Internal_Reference STRING64
NA
A value that is used internally within the organization to reference this activity. No
VARCHAR2(64)
Lagged_Samples_Flag boolean
NA
A flag to denote whether a lagged samples were taken during the period of this report. No
NUMBER(1)
Name ENTITY_NAME
NA
The name given to any object or data item, e.g. Name of Well, Name of Field, etc. No
VARCHAR2(255)
Original_Source STRING64
NA
The name of the person, Organization or project source that originally provided this entity, e.g. "IHS-EnergyData" or "FinderUpper Stratton Deeper Pool 15" No
VARCHAR2(64)
Produced_By STRING64
NA
ID of the activity that was executing when the entity was created, for data created programmatically. No
VARCHAR2(64)
Purpose STRING255
NA
A description of purpose of the activity or its stage No
VARCHAR2(255)
Remarks STRING2000
NA
Any type of remarks added to an entity instance. No
VARCHAR2(2000)
SDAT_Label int
No_Unit
Label used by the security system for entitlements. SDAT is Secure Data Access Technology. No
NUMBER(10)
Source STRING64
NA
Name of the person or organization responsible for this entity"s E and P content and quality. Not the data technologist or IT expert creating the entity, for which see IT_Object.Insert_User and Update_User. No
VARCHAR2(64)
Start_Date DATE
NA
The date and time at which the activity will start or did start. For planned activities, this would be expected start date. No
DATE
Start_MD double
Depth
Measured depth at the start of the activity or proposed start depth of the activity. No
NUMBER
Successful_Flag boolean
NA
A flag to indicate whether or not the activity was successful (Yes/No) No
NUMBER(1)
Time_Offset double
Time
The time offset from the start of the program that this activity is scheduled to start at. This is normally used while planning a job. No
NUMBER
Transient_Period R_Transient_Period
Indicates whether the activity is executed daily, monthly, on demand, etc. No
VARCHAR2(64)
Triggering_Event_Id Event
The identifier of the event that triggered the start of this activity. Events can trigger activities. For example, an explosion event could trigger a firefighting activity. Note that this value should not conflict with, or be confused with, the value in Activity_Status.Triggering_Event. No
NUMBER(38)
Trip_Chloride_Conc double
Concentration
Concentration of chloride ions in water-based mud or in the water phase of oil-based mud recorded during a trip. No
NUMBER
Update_Date DATE
NA
Date of the most-recent modification to the entity. No
DATE
Update_User STRING64
NA
The name of the user responsible for the last modification to this entity. No
VARCHAR2(64)
Version STRING255
NA
The form or variant of the entity. Yes
1
VARCHAR2(255)
Work_String_Id Work_String
The work string used during a borehole activity. No
NUMBER(38)


Refers To

[Previous] [Next] [Top]
LinkTo EntityDescriptionImplementation TechniqueRequired
Work_String Work_String _ Restrict No
Borehole_Section Borehole_Section _ Assoc to Many No
Borehole_Zone Borehole_Zone _ Assoc to Many No
Borehole Borehole _ Cascade Yes
Activity_Program Activity_Program _ Restrict No
Transient_Period R_Transient_Period _ Restrict No
Super_Activity Activity _ Assoc to One No
Fulfilled_Activity Activity _ Assoc to Many No
Triggering_Event Event _ Nullify No
Activity_Template Activity_Template _ Restrict No


[Seabed Objects] [Entities in Schema Seabed] [Index]